Era Valdivia Contractors, Inc. (Chicago, IL) was awarded a contract of $4,490,075.80 by the Wisconsin Department of Transportation to recoat dual, 2,380-foot-long steel girder bridges over the St. Croix River. A total of approximately 510,000 square feet of steel will be abrasive blast-cleaned to a Near White finish (SSPC-SP 10) and recoated with a zinc primer, an epoxy intermediate, and a urethane finish. The project also includes coating the bottom twenty feet of nine, 100-foot-tall high mast lights. The owner is requiring the use of negative-pressure containment to control emissions of the existing coatings, which are presumed to contain lead.
Reported by Paint BidTracker.
|